dhodges3
Civil/Environmental
- Dec 1, 2010
- 1
I have a site where we are putting a detention pond that will need a lift station. With the new requirements to show the 10-yr and 100-yr WSEs, I'm not really sure how to model this or come up with the WSEs. Do I need to set the system to have a set discharge rate (and would it be the 100-yr rate or the 10-yr rate)? I can't seem to wrap my head around how to even start modeling this.
Any help would be appreciated!
Thanks!
Any help would be appreciated!
Thanks!