bdn2004
Electrical
- Jan 27, 2007
- 794
Attached is a 4page pdf of the single line, the vendor prints and a TCC of a 12.47kV switchgear ground curves.
We worked out the phase settings on the Main breaker to coordinate with the Utility, but I'm confused about the 51N settings. The Utility said to set them the same as the phase settings. That doesn't seem right even though the curves look coordinated. I didn't think the 51N worked on line currents but on differential current and its supposed to be a definite time setting. Any thoughts ?
We worked out the phase settings on the Main breaker to coordinate with the Utility, but I'm confused about the 51N settings. The Utility said to set them the same as the phase settings. That doesn't seem right even though the curves look coordinated. I didn't think the 51N worked on line currents but on differential current and its supposed to be a definite time setting. Any thoughts ?