Hi all,
Looking for some tips on best practices in HP steam pipework design in thermal power plant (design pressure up to 200 bar).
I appreciate that there are a number of variables here, but my first question is, at heat exchanger / steam drum nozzles and at valves, would it be the usual practice in power plant design to direct weld these joints, where flanges are not required for regular maintenance?
Second question, where direct welded joints are used at heat exchangers and at valves, would it be the normal practice to re-hydrotest these items of equipment as part of the assembled system at site, or would these joints typically be considered as "golden joints".
Any guidance or references to literature for further reading would be appreciated. Thanks.
Looking for some tips on best practices in HP steam pipework design in thermal power plant (design pressure up to 200 bar).
I appreciate that there are a number of variables here, but my first question is, at heat exchanger / steam drum nozzles and at valves, would it be the usual practice in power plant design to direct weld these joints, where flanges are not required for regular maintenance?
Second question, where direct welded joints are used at heat exchangers and at valves, would it be the normal practice to re-hydrotest these items of equipment as part of the assembled system at site, or would these joints typically be considered as "golden joints".
Any guidance or references to literature for further reading would be appreciated. Thanks.