HofOblivion
Structural
- Dec 15, 2014
- 13
I have a project where hillside ordinance is applied. One side of the building is fully day-lighted (T.O. soil and T.O.S. at the same elevation) and the other side is retaining soil up to 8'-0" height. I cannot determine if the I have to assume the base level diaphragm at the roof level (at 10'-0" above the T.O.S.) or at the slab as the building cuts into the (E) soil. Which is the correct way to design this building?