Aye, there's the rub...
The configuration of the wall is such that there are no anchor rods. And... using double-channels isn't an option...
Here's what I've got: two 24-inch concrete-filled caissions act as soldier piles, they're spaced at some distance. Between them - and covering them - is a concrete wall. If you didn't know about the soldier piles, you'd think the wall was simply a reinforced concrete T-wall. Well, let me be more clear: the concrete wall is fronted by sheet piling.
Because of customer constraints (totally out of my control as I'm being directed by a much more senior engineer than I) the wall cannot exceed a certain thickness. The much more senior engineer than I directed me to put a waler (for lack of a better term) between the caissions in case the reinforced concrete cannot take the loads (these being wave loads). OK, even though I designed the wall for these loads, there's no harm in beefing up the design since the money is there, etc., etc.
So I came up with a "waler" (OK, this is more like a vierendeel truss-frame system than a soldier pile wall, no?) that was adequate for the loads in question and layed it out in what I figured was appropriate:
A lightest-weight W shape (like a W18xless-than-100lbs/foot) would be connected to the caissions such that the centerline of the caissons and the waler (strong-axis facing horizontal) lining up. This allowed enough inches for placing rebar in front of the waler and in back of the waler as my wall design required. The wall would be poured in lifts, the first up to the waler, then the waler is connceted, then complete the wall in a second lift, keying appropriately into the first pour, etc.
The senior engineer became concerned that torsional effects would cause cracking in the concrete and to avoid this I should bolt the waler to the sheet pile. OK, if I do that I lose the symmetry (centerlines of caisson - centerline of the waler, etc.) of the connection and the waler requires that the vertical rebar be discontinous as the waler is now in the way.
"Cut holes in the waler and call-out the rebar to be continuous through the waler."
These are #8 bars. So.... 8/18 = .44444 > .33333.
I don't like the idea, frankly of cutting holes in the waler as, well, it just doesn't seem correct and would add a lot of cost to construction (a lot of holes...).