Civilfreak
Structural
- Apr 26, 2016
- 3
Hi,
In BS 8500-1-2016, Annex C, we can find target cement content for each prescribed ratio mix. For example if its 1:1:2 ratio, target cement content is 480 kg/m3 as per BS 8500-1. I have attached Annex C for reference. Can someone explain how they have derived 480 kg/m3 for mix ratio 1:1:2 ? I would like to know how they have calculated 480 kg/m3 for 1:1:2 mix ratio.
In BS 8500-1-2016, Annex C, we can find target cement content for each prescribed ratio mix. For example if its 1:1:2 ratio, target cement content is 480 kg/m3 as per BS 8500-1. I have attached Annex C for reference. Can someone explain how they have derived 480 kg/m3 for mix ratio 1:1:2 ? I would like to know how they have calculated 480 kg/m3 for 1:1:2 mix ratio.