Hi All,
I'm having an issue calling out the welding procedure correctly. I have two beams intersecting and sitting on top of an embedded plate. I would like there to be weld between the embedded plate and the connection between the two surfaces of the bottom flanges of beams.
I imagine there to be a first pass to bring the embed plate to one of the surfaces of the beams, then a final weld to close up the entire gap (pull depth groove weld). It's the first weld I am unclear on.
Thank you