Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations IDS on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

How to get a load profile 2

Status
Not open for further replies.

analystuc

Mechanical
Oct 15, 2008
15
Please I am not conversant with electrical systems. But I was asked by a power plant vendor to provide an electrical load profile for a fertiliser plant to enable them to select an appropriate power plant configuration. How and where do I start from.
 
Replies continue below

Recommended for you

Yellow pages under Engineering, Consulting, Electrical.

Bill
--------------------
"Why not the best?"
Jimmy Carter
 
@ waross
Thanks for your suggestion anyway. I guess one pays for this kind of thing. But I would still appreciate a little insight into the process of getting a load profile. Maybe a pinch of information would set me on the right track towards getting consultant help.
 
Electrical power demand varies over each day and throughout the year.

In the case of a cogeneration facility, I expect they will want to know the peak power demand each month for the past year as well as the kWh and kVarh usage for each month over the past year or two. Some of this data can probably be obtained from the power company, some from the local plant metering, and some may have to be obtained via use of portable power monitoring equipment.





"Theory is when you know all and nothing works. Practice is when all works and nobody knows why. In this case we have put together theory and practice: nothing works... and nobody knows why! (Albert Einstein)
 
A load profile is a description of the electrical load for the facility under various operating conditions: startup, standby, full capacity,etc. It lists the magnitude and duration of the loads. If the plant is existing, record the actual loads for a month or more at the utility service, noting peak KW, average KW and other factors, such as size of largest motor.

If the plant is under design, determine the size of all electrical motors and loads in the plant and when they will be running. Sum the loads that are running for each different operating mode and determine how long each mode will last. Develop a chart or graph or table showing the various loads and timing.

The power plant personnel want to know how much power the fertilizer plant will need under all operating conditions and how long each condition lasts. The peak load requirement determines the size of the generating plant. The average load determines if there is enough revenue to cover capital costs.

Start by gathering all of the individual load data and a description of how the plant operates. Then hire a knowledgeable consultant.
 
I appreciate your reply. I guess peopla are paid for this sort of thing.But I would really appreciate any snippet of information for a headstart. This would make things easier when looking for a consultant.
 
I think you have several snippets already.

"Theory is when you know all and nothing works. Practice is when all works and nobody knows why. In this case we have put together theory and practice: nothing works... and nobody knows why! (Albert Einstein)
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor