mdmiller
Structural
- Jul 12, 2004
- 13
I have an existing precast double tee floor that according to the shop drawings was only designed for 40 psf LL and 15 psf DL. The owner wants to hang a 1/2 ton hoist and rail to the underside of the precast tees. I expect the point load from the hoist to be around 1.6 kips.
How can I reinforce the existing double tee to support the new hoist load?
THANK YOU!!!
How can I reinforce the existing double tee to support the new hoist load?
THANK YOU!!!