X60
Petroleum
- Feb 8, 2007
- 7
We have been supplying a belt and braces Total Elf Fina job and they have waived the Hydro-Test in favour of the Mnfr guaranteeing that the base material (pipe) was Hydro tested at the mill at point of production. However, it seems that the mnfr cannot verify this for one fitting and now Bureau Veritas have insisted a Hydro Test must be undertaken on this one fitting. Does anyone know a cheap and effective method of doing this test without the need for butt weld caps and blind flanges? Gratful for any help/suggestions.