Hi !
I am working as contractor side QC Inspector (Piping) in a Project. Shell is our Client. During hydrotest we are advised to remove the preservation layer we made on pipe/fittings in order to witness the long seam (26”/30” sizes) welds.
As per ASTM A403 (Standard Specification for Wrought Austenitic SS Piping Fittings) 9.1 hydrotest is not required for fittings.
But our client argued that those fittings already installed as a part of process piping, so as per B31.3 all weld should be witnessed during hydrotest. Hence advised us to witness the long seam welding of pipe/fittings.
Pls advise on this.
I am working as contractor side QC Inspector (Piping) in a Project. Shell is our Client. During hydrotest we are advised to remove the preservation layer we made on pipe/fittings in order to witness the long seam (26”/30” sizes) welds.
As per ASTM A403 (Standard Specification for Wrought Austenitic SS Piping Fittings) 9.1 hydrotest is not required for fittings.
But our client argued that those fittings already installed as a part of process piping, so as per B31.3 all weld should be witnessed during hydrotest. Hence advised us to witness the long seam welding of pipe/fittings.
Pls advise on this.