zebco
Civil/Environmental
- Apr 13, 2009
- 18
I guess I need some reassurance or correction.
I'm developing hydrographs.
I've got a project under review, the Tp or times to peak are being questioned, I kinda question them too.
Scenario, 0.22 acre site, pre-development is all woodland (0.4C), post-development is a roadway with C&G (0.96C).
Time to peak flow calculates as 4 minutes pre and 26 minutes post development. 300 foot reach 5% slope. Does this sound reasonable?
I'm developing hydrographs.
I've got a project under review, the Tp or times to peak are being questioned, I kinda question them too.
Scenario, 0.22 acre site, pre-development is all woodland (0.4C), post-development is a roadway with C&G (0.96C).
Time to peak flow calculates as 4 minutes pre and 26 minutes post development. 300 foot reach 5% slope. Does this sound reasonable?