66851230797
Mechanical
- Nov 29, 2008
- 2
I have to fabricate pressure vessel made by SA516 Gr.70 (ASME section I,shell thickness is 140mm)with using 2 plates per 1 shell course. Our fabricator propose to weld 2 plate together and then rolling to the expected diameter. WPS/PQR require preheat and PWHT as per code requirement.
Our fabricator propose to preheat and weld the plates together without PWHT at this step and then roll the plate to make shell course,PWHT will be done after complete all pressure vessel welding as a final PWHT.
Could I ask whether this procedure can be done and acceptable by ASME and there are any ASME code state about this? or we need to complete PWHT as per WPS of the weld joint before rolling.
Our fabricator propose to preheat and weld the plates together without PWHT at this step and then roll the plate to make shell course,PWHT will be done after complete all pressure vessel welding as a final PWHT.
Could I ask whether this procedure can be done and acceptable by ASME and there are any ASME code state about this? or we need to complete PWHT as per WPS of the weld joint before rolling.