The latest project that I'm working on is in a remote, undeveloped region in Indonesia. We'd like to use the latest code, IBC 2003. However, there are no Ss & S1 charts for earthquake design, and our client will never spend the money or time for the incredible amount of research that would be required to develop these local values. I can't blame them. The site is barely accessible.
We are currently using UBC 1997, zone 3 for design. Are we now locked in with UBC forever? Will we be forced to use UBC 1997 20 years from now and not able to take advantage of code advancements?
We are currently using UBC 1997, zone 3 for design. Are we now locked in with UBC forever? Will we be forced to use UBC 1997 20 years from now and not able to take advantage of code advancements?