We have just started design of a large institutional project in which the architect wants to use ICF (Insulated Concrete Forms) Walls. Our initial reaction was positive since we would be designing basically 8" solid concrete walls. However we have since heard 'horror' stories about recent projects where substantial voids were encountered in the wall system.
Since the insulation stays in place, it would seem difficult to verify full coverage throughout the wall system.
Has anyone run into similar problems or determined ways to review on site.
Thanks
Since the insulation stays in place, it would seem difficult to verify full coverage throughout the wall system.
Has anyone run into similar problems or determined ways to review on site.
Thanks