Hi guys,
I would like to seek clarification sentences on IEC 60076-5 2000 clause 3.2.7 Tap-changing equipment.
Where fitted, tap changing equipment shall be capable of carrying the same overcurrents due to short-circuits as the windings. However, the on-load tap-changer is not required to be capable of switching the short-circuit current.
What is the difference between tap changing equipment and on-load-tap-changer ?
I would like to seek clarification sentences on IEC 60076-5 2000 clause 3.2.7 Tap-changing equipment.
Where fitted, tap changing equipment shall be capable of carrying the same overcurrents due to short-circuits as the windings. However, the on-load tap-changer is not required to be capable of switching the short-circuit current.
What is the difference between tap changing equipment and on-load-tap-changer ?