SCERS
Electrical
- Sep 24, 2014
- 3
Can anybody tell me if they relate practices from IEEE 43-2000 "Recommended Practice for Testing Insulation Resistance of Rotating Machinery" to transformers. My specific question is if when performing a P.I. on a transformer, if your 60 second reading is greater than 5000 megohms, do you continue until 10 minutes, or abandon testing?