BRIS
Civil/Environmental
- Mar 12, 2003
- 525
I am costing a project including a pump station. The project will take power from a 220 kV supply through a 220/11kv sub-station. The pump station will have an 11 kV supply.
Pumps are 2 duty one standby each rated at 650 kW. The Preliminary design shows 11 kV motors with DOL. Pumps are fixed speed.
My rule of thumb is 3.3kV motors up to about 1.3 MW.
1) is it practicle, feasable and economic to use 11 kV motors. Is it more likely that the design/build contractor will transform down to 3.3 kV and use 3.3 kV motors.
I could change the specification from 2 duty 1 standby each rated at 650 kw to 1 duty one standby each rated at 1.3 MW.
Obviosly what I ned to do is a propoer costed study but I don't have time. Any good rules of thumb?
Pumps are 2 duty one standby each rated at 650 kW. The Preliminary design shows 11 kV motors with DOL. Pumps are fixed speed.
My rule of thumb is 3.3kV motors up to about 1.3 MW.
1) is it practicle, feasable and economic to use 11 kV motors. Is it more likely that the design/build contractor will transform down to 3.3 kV and use 3.3 kV motors.
I could change the specification from 2 duty 1 standby each rated at 650 kw to 1 duty one standby each rated at 1.3 MW.
Obviosly what I ned to do is a propoer costed study but I don't have time. Any good rules of thumb?