Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations SDETERS on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

I'm helping out with a dedign to fi

Status
Not open for further replies.

mattradk

Civil/Environmental
Jul 23, 2016
22
I'm helping out with a dedign to finish about half of a basement to make a playroom.

The basement walls are 8" concrete block, and the floor is poured concrete with a weep well around the whole basement perimeter that leads to a sump well and pump. The sump pump and well are not in the area where the playroom would be.

The present plan to finish the exterior walls is to first put vertical treated 2x studs as nailers flat on the concrete wall, then mount 3" rigid insulation on the nailers (R15 required in our area), then build a regular 2x4 stud wall against the rigid foam (with a treated shoe), and finally, place mold resistant drywall against the stud wall that will be painted.

The purpose of the initial 2x nailers is to avoid covering the weep wells with the rigid insulation, and to provide some vertical ventilation for the weep well.

Right now, no ceiling is planned .... just the walls and an epoxy-leveled floor covered by engineered flooring specified for this kind of application.

The basement had a moisture problem before the owner bought the house (not water but moist walls), but it was remediated by a basement contractor who installed the sump well and pump, as well as a dehumidification and gutter system that leads to a dry well. It's been pretty dry throughout the unusually wet summer we've had this year.

Does this sound like a reasonable way to deal with the weep wells? Or should they be ignored since they haven't been observed with any significant moisture in them? In that case, the treated 2x's against the wall could be omitted.

Thanks!
 
Replies continue below

Recommended for you

This is just me, but I am not a fan of finishing a basement right up against the foundation wall. In fact, when I can, I specify a 24 inch wide void between the foundation and partition wall, so you can get back there and at least check the foundation, and avoid nailing into the CMU. This is particularly useful when water management systems (sumps, dehumidification) are installed. In 2021 alone, I've had 21 projects where face partition walls had to be partially removed to get at mold or areas of the foundation that needed repairs.

As far as the gap between the slab and foundation, they need to be kept clean of debris. But it usually takes decades to clog them up.

So for me, given a CMU foundation that has had past water intrusion issues and a newer water management system installed, you wouldn't catch me dead trying to install framed walls right up against the foundation.
 
24" clear isn't going to be very practical, except at reducing the cost of flooring and ceiling material and the value of the space as it gets so much smaller. The cost/useable ft2 is going to go up pretty high. I'd be temped to first test a waterproof sealing compound, such as It might also cost some too, but you would have the space to play in. Maybe there is an optimum space vs cost of each option. I'd like to find out what it might be.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor