I would like to import an external schedule into a master schedule I have but, they have different calendar options.
The master schedule has its calendar options set to 7 hr/day, 35 hr/wk. The external schedule has its option set to 8 hr/day, 40 hr/wk. This obviously affects how project is converting the task duration into hours. A task that was once 1 day is now 1.14 days.
I tried changing the master schedule's calendar options and then importing the external schedule because I thought the ratio was only affected one time at import and then change the master schedule's calendar options back.
I have many external schedules to import so, I am trying to avoid manually correcting each duration.
Any advice?
The master schedule has its calendar options set to 7 hr/day, 35 hr/wk. The external schedule has its option set to 8 hr/day, 40 hr/wk. This obviously affects how project is converting the task duration into hours. A task that was once 1 day is now 1.14 days.
I tried changing the master schedule's calendar options and then importing the external schedule because I thought the ratio was only affected one time at import and then change the master schedule's calendar options back.
I have many external schedules to import so, I am trying to avoid manually correcting each duration.
Any advice?