Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations GregLocock on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

in service Ultrasonic Inspection

Status
Not open for further replies.

gemcan

Petroleum
May 22, 2003
1
I would like to know the procedures for Inspection of High Pressure/ Low pressure Vessels without shut down of operation. The inspection is for Corrosion testing etc. The Ultrasonic Inspection.
 
I take it that the safety of the inspector is not a priority for your organization! If this is so, just use a high temp couplent and a stand-off to protect the transducer from thermal failure.
 
the procedure is the same whether on line or off apart from the need to use a high temperature couplant and a high temperature probe but as we dont know what the temperature of your vessels are this is just for information. As long as you can safely access the vessel it can be done without problems. you probably need to scaffold , and may need to remove insulation if it exists other wise being in service makes no difference

 
See ASTM SE-797
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor