JXWu
Petroleum
- Oct 26, 2015
- 24
Hi,
I fabricated 800H pipe welded with Inco 82 filler, performed stabilising annealing at 985 deg C for 3 hours.
Specified code is B31.3 and the service temperature is 850 deg C.
Client specifies a maximum cooling rate of 150 deg C/hr but we exceed this cooling rate. Actual cooling rate is 180 deg C/hr.
I looked up B31.3 and there is no requirement for cooling rate. ASME VIII says it up to agreement between user and manufacturer.
Basically we did not meet client's spec. but I would like to know if the increase in the cooling rate by 20 dec/hr is harmful to the welds before getting client to accept the weld as it is.
If these welds are rejected, can I repair them by going through another cycle of heat treatment?
Thanks.
I fabricated 800H pipe welded with Inco 82 filler, performed stabilising annealing at 985 deg C for 3 hours.
Specified code is B31.3 and the service temperature is 850 deg C.
Client specifies a maximum cooling rate of 150 deg C/hr but we exceed this cooling rate. Actual cooling rate is 180 deg C/hr.
I looked up B31.3 and there is no requirement for cooling rate. ASME VIII says it up to agreement between user and manufacturer.
Basically we did not meet client's spec. but I would like to know if the increase in the cooling rate by 20 dec/hr is harmful to the welds before getting client to accept the weld as it is.
If these welds are rejected, can I repair them by going through another cycle of heat treatment?
Thanks.