gravitate
Mechanical
- Aug 17, 2012
- 80
We have 2 stainless DN 600 pipes to go side by side in a 750 x 3500 shaft. Is this space too small to install the pipe in sections welding every 6m or would it be preferable to get the pipe delivered while the building is in construction and lift the pipes in 1 length then weld at the top and the bottom?
The rest of the space in the shaft will be used for HVAC but if the pipe is early and lifted in 1 go then the HVAC will not be there.
I find it hard to imagine the space restrictions as the building is not built yet.
Thanks
The rest of the space in the shaft will be used for HVAC but if the pipe is early and lifted in 1 go then the HVAC will not be there.
I find it hard to imagine the space restrictions as the building is not built yet.
Thanks