MrEngineerUS
Structural
- Apr 9, 2013
- 46
I've been informed that the contractor is hitting 6-7" diameter rocks during the installation of the sheet piles for a braced excavation I've designed. They would like to essentially not drive the piles to the required depth.
The braced excavation is roughly 7 feet deep and the piles should be driven to at least 9.5 feet per my design. They want to stop driving piles that encounter these rocks at generally 1.5'-2' short of the designed depth. There are two levels of walers and struts that are to be installed as the excavation progresses.
My question is what is typically done in a scenario such as this? Do I just tell them that it needs to be installed to the required depth and that it's a means-and-methods item? Can they just locally excavate and remove the rocks as they are encountered? I've been told that it isn't just a pile here and there but could be 3-4 piles in a row with this condition.
Thanks for any comments! I don't have much experience with the installation and resulting field issues of these sorts of walls.
The braced excavation is roughly 7 feet deep and the piles should be driven to at least 9.5 feet per my design. They want to stop driving piles that encounter these rocks at generally 1.5'-2' short of the designed depth. There are two levels of walers and struts that are to be installed as the excavation progresses.
My question is what is typically done in a scenario such as this? Do I just tell them that it needs to be installed to the required depth and that it's a means-and-methods item? Can they just locally excavate and remove the rocks as they are encountered? I've been told that it isn't just a pile here and there but could be 3-4 piles in a row with this condition.
Thanks for any comments! I don't have much experience with the installation and resulting field issues of these sorts of walls.