Gopher13
Structural
- Jun 21, 2016
- 94
I have a question about what is typically done at the interface of interior non-load bearing and load bearing cmu walls at the slab elevation. Should the thickened slab for the non-load bearing wall be poured directly on top of the load bearing footing, or should there be a layer of soil between the two? Please see the attached sketch for reference. Thanks!!!