Mad Mike
Geotechnical
- Sep 26, 2016
- 220
I'm currently running the geotechnical control on a large-scale industrial development on South Africa's east coast.
The larger development platforms are in the 10 - 20Ha range, developed over a site underlain by hard rock sandstone mantled by sandy soils. Due to the enormous volumes of hard rock, the previous geotechnical consultant incorporated a few rock-fill embankments into the development, which are now being carried over to my involvement.
The rock fill is being constructed by blending sound, blast rock sandstone of acceptable size with the sandy soils and compacting in layers of 750mm using heavy impact plant.
I have drawn the engineer's attention to the fact that rock-fill limits the founding options for the top-structures (which in this case are generally warehouse structures but often with fairly heavy gantries) and he is unfazed, being of the impression that all elements can be founded shallowly on pad footings.
Under normal circumstances I wouldn't be concerned- the fill layers are being engineered to a very high standard. However, the fill thickness in several areas approaches 30m (100ft).
I am now being asked by structural engineers to estimate the settlements beneath shallow foundations, specifically for a platform that has been standing for 1 year, with several good rains having occurred since construction. Note that there are no compressible soils beneath these enormous rock-fill embankments and my gut feel is that internal fill settlement will be negligible.
I would greatly appreciate any advice on fill shrinkage in well engineered rock-fills...I'm aware of all the rules of thumb for settlement estimation but this is not a conventional fill and I'm wary. My recommendation to the engineer / contractor was to monitor the embankment settlement at platform level, which they did, but the readings consistently came back as around 0mm and I have grave doubts as to the accuracy of the survey. I am now in a position where time is of the essence so will have only my own judgement to go by.
Sincerely,
Mike
The larger development platforms are in the 10 - 20Ha range, developed over a site underlain by hard rock sandstone mantled by sandy soils. Due to the enormous volumes of hard rock, the previous geotechnical consultant incorporated a few rock-fill embankments into the development, which are now being carried over to my involvement.
The rock fill is being constructed by blending sound, blast rock sandstone of acceptable size with the sandy soils and compacting in layers of 750mm using heavy impact plant.
I have drawn the engineer's attention to the fact that rock-fill limits the founding options for the top-structures (which in this case are generally warehouse structures but often with fairly heavy gantries) and he is unfazed, being of the impression that all elements can be founded shallowly on pad footings.
Under normal circumstances I wouldn't be concerned- the fill layers are being engineered to a very high standard. However, the fill thickness in several areas approaches 30m (100ft).
I am now being asked by structural engineers to estimate the settlements beneath shallow foundations, specifically for a platform that has been standing for 1 year, with several good rains having occurred since construction. Note that there are no compressible soils beneath these enormous rock-fill embankments and my gut feel is that internal fill settlement will be negligible.
I would greatly appreciate any advice on fill shrinkage in well engineered rock-fills...I'm aware of all the rules of thumb for settlement estimation but this is not a conventional fill and I'm wary. My recommendation to the engineer / contractor was to monitor the embankment settlement at platform level, which they did, but the readings consistently came back as around 0mm and I have grave doubts as to the accuracy of the survey. I am now in a position where time is of the essence so will have only my own judgement to go by.
Sincerely,
Mike