SteelPE
Structural
- Mar 9, 2006
- 2,743
I have a residential project where the contractor ran into some poor soils conditions when they were excavating for the foundation. The contractor decided to place the footing for the residence on top of virgin ground vs a controlled backfill (which was a wise decision considering who I am dealing with). Now, I will have a foundation wall that is quite tall (upwards of 14'-0") but the unbalanced backfill height is only planned to be 8'-0" (see sketch... for reference, a wood framed floor will be placed at the top of the concrete wall). My question is in relation to IRC table R404.1.2(8) and the "Maximum Wall Height" and "Maximum Unbalanced Backfill Height" as outlined in this table.
As I am looking at this table, it would appear as if the wall in question is outside the purview of the IRC as the wall height is greater than 10'-0". However, if the contractor decided to backfill vs place the footing on virgin soil, then our wall height would fall within the IRC.
1) Should this wall be engineered utilizing normal engineering methods as a cantilever retaining wall(I am figuring a 6'-0" wide footing with a 12" foundation wall reinforced with #6@12" o.c.)?
or
2) Would you twist the code a bit and allow for this wall to fall under the purview of the IRC (utilizing a 2'-0" wide footing and a 10" thick foundation wall)?
As I am looking at this table, it would appear as if the wall in question is outside the purview of the IRC as the wall height is greater than 10'-0". However, if the contractor decided to backfill vs place the footing on virgin soil, then our wall height would fall within the IRC.
1) Should this wall be engineered utilizing normal engineering methods as a cantilever retaining wall(I am figuring a 6'-0" wide footing with a 12" foundation wall reinforced with #6@12" o.c.)?
or
2) Would you twist the code a bit and allow for this wall to fall under the purview of the IRC (utilizing a 2'-0" wide footing and a 10" thick foundation wall)?