Uprising
Structural
- Jan 19, 2012
- 11
When designing a reinforced masonry wall, I was taught by a previous Engineer that if all the cores are grouted filled then a bond beam was not required.
Today I was looking over another Engineer's design who had specified that all cores be grout filled, with N12 at 400 vertically and horizontally and a bond beam in the top course (supporting a roof structure only).
I couldn't really find an answer today; the AS 3700 specifies that "Bond beams shall be provided at the top of all walls, where the wall is supporting a floor and under all windows wider than 1500 mm".
Most typical details show a bond beam being using in the top course. Is a bond beam always required or can it be omitted if all the cores are grout filled and only supporting a roof?
Today I was looking over another Engineer's design who had specified that all cores be grout filled, with N12 at 400 vertically and horizontally and a bond beam in the top course (supporting a roof structure only).
I couldn't really find an answer today; the AS 3700 specifies that "Bond beams shall be provided at the top of all walls, where the wall is supporting a floor and under all windows wider than 1500 mm".
Most typical details show a bond beam being using in the top course. Is a bond beam always required or can it be omitted if all the cores are grout filled and only supporting a roof?