Dear all engineers,
on our project we already ordered pipe with 78" size in service to flow gas to a new flare stack. but cause of some condition, we must idle the pipe and stack until 3 years from now. the flare stack is installed to a derrick structure along with another new flare stack but different line track. My question is :
1. is it possible to do internal coating on site to this 78" pipe because we already send it to the site?
2. How many the duration needs approximately to finish the internal coating work?
3. and whats the minimum thickness of the coating?
thank you all.
Warm regards.
on our project we already ordered pipe with 78" size in service to flow gas to a new flare stack. but cause of some condition, we must idle the pipe and stack until 3 years from now. the flare stack is installed to a derrick structure along with another new flare stack but different line track. My question is :
1. is it possible to do internal coating on site to this 78" pipe because we already send it to the site?
2. How many the duration needs approximately to finish the internal coating work?
3. and whats the minimum thickness of the coating?
thank you all.