yddkdd
Civil/Environmental
- Sep 15, 2005
- 4
I am planning an addition to my home. My lot slopes to the back, so I am contemplating installing a 3-sided basement with access from the street. Due to site limitations, I do not have alot of room to accommodate the side slopes. So I am planning to excavate to get a working area, form up my walls with ICF block, then pour. All of the work will be done from the inside of the proposed walls, or from the outside at the top level without going into the excavation. (bracing, etc.)
So...
1. Is this a trench ? (see attachment)
2. Does OSHA apply if I have no employees and am doing the work myself ?
I know that OSHA has soils grades ABC, but my geotech report says that I can excavate vertically for 6'...
So...
1. Is this a trench ? (see attachment)
2. Does OSHA apply if I have no employees and am doing the work myself ?
I know that OSHA has soils grades ABC, but my geotech report says that I can excavate vertically for 6'...