ISO 13847 WPQR qualification

Status
Not open for further replies.

mohamed fayez

Petroleum
Dec 31, 2021
1

what is meant by supply condition in iso 13847 clause 7.6.3.3 Supply condition
shall i perform a separate wpqr for each type of fitting (flange , elbow , tee , weldolet)
 
Replies continue below

Recommended for you

Heat treated, cold worked, etc etc. The material condition rather than the product form.

Steve Jones
Corrosion Management Consultant


All answers are personal opinions only and are in no way connected with any employer.
 