We propose to use jet grout columns to create a foundation to support a relatively small rock breakwater. The columns will be constructed approx 20m into the seabed (depth of water averaging 10m). Has anyone any experience on this type of project, one concern is environmental issues from escape of the binder at the seabed. Our contractor intends first to jack in a casing to about 3m below the seabed then install the jet grout equipment within the casing, pumps will take the excess material from the casing back to the barge.