I am trying to join ASTM A514 or 4142 to its self by EB welding. I have questions
1.) Is it required to pre prior to welding and post heat after welding?
2.) If the pre is 450 deg F does it have to be 450 or in transering from the oven and parts are 375 deg F is that good enough?
3.) Post heating does it have to happen immediatly after turning off the beam or can tha parts cool to 200 deg F priot to heating up to 600 deg. F?
4.) I know this material is prone to cracking due to hardening at the weld joint. Should your heating be in the Vacuum chamber?
1.) Is it required to pre prior to welding and post heat after welding?
2.) If the pre is 450 deg F does it have to be 450 or in transering from the oven and parts are 375 deg F is that good enough?
3.) Post heating does it have to happen immediatly after turning off the beam or can tha parts cool to 200 deg F priot to heating up to 600 deg. F?
4.) I know this material is prone to cracking due to hardening at the weld joint. Should your heating be in the Vacuum chamber?