Doing a retrofit job at a wastewater facility where the exist. system is cement lined ductile iron pipe with a combination of mech. jt. fittings and Victaulic fittings.
Question, when making a tie-in to an exist. 12" D.I.P. with
a flanged tee, how is the mating joint made?
1. by threading the exist. pipe in place and installing a mating flange?
2. via a new flg. spool and a grooved cplg?
Doing a retrofit job at a wastewater facility where the exist. system is cement lined ductile iron pipe with a combination of mech. jt. fittings and Victaulic fittings.
Question, when making a tie-in to an exist. 12" D.I.P. with
a flanged tee, how is the mating joint made?
1. by threading the exist. pipe in place and installing a mating flange?
2. via a new flg. spool and a grooved cplg?