CJBHM52
Civil/Environmental
- Feb 24, 2009
- 10
I am working on a slab on grade design for a PEMB. Slab will have turned down perimeter footing and will be poured monolitically with column footings. Soils are not ideal and there will be heavy equipment loads (forklifts, loaders). Slab will be 12" with double mat of rebar. So how do the joints work? If I am reading ACI 360 right, it is recommended to install dowels or plates along each saw cut joint? That doesn't seem practical for a large slab (14,000 sf). What about leaving the bottom mat of rebar continuous across joints and breaking the top mat at each joint? There would be certain joints that would be doweled, but not every one. The main frames are spaced at 33', so I was thinking about putting one joint along the frame line and one between each frame (16.5' oc) and 15' oc perpendicular to the main frames. Are there any potential problems with a joint running into the column footing when the footing is poured monolithic with the slab? We wouldnt sawcut over the footing though, it would stop at the footing. Thanks in advance.