LittleGator
Structural
- Dec 23, 2008
- 1
The minimum drilled shaft embedment length we use 1.33 times is the length at which additional embedment does not result in a reduced deflection at the pile head (TxDOT Guide).
Since lateral deflection is a service limit state, should we use service loads when we run LPILE to develop the deflection versus embedment table? Is the factor of safety the 33% increase in shaft length? Or, does the Geotechnical Engineer include the factor of safety in the soil properties they provide? Or, should load factored (strength) inputs be used?
Since lateral deflection is a service limit state, should we use service loads when we run LPILE to develop the deflection versus embedment table? Is the factor of safety the 33% increase in shaft length? Or, does the Geotechnical Engineer include the factor of safety in the soil properties they provide? Or, should load factored (strength) inputs be used?