Everynameistaken
Structural
- Jun 29, 2014
- 68
Hi All,
I have a question regarding building a built-up timber beam out of 2x12
We have spec'd solid sam members and they cannot get them in time.
The code has tables for 5-ply built-up sections but does anyone see any reason why a 6-ply would be a problem? Need it for capacity.
As an alternate I could try 2 4-ply built-up beams. Make the 4-ply beams with nails per the code, them thru bolt the two built-up beams together to get a new huge beam??
Thoughts?
I have a question regarding building a built-up timber beam out of 2x12
We have spec'd solid sam members and they cannot get them in time.
The code has tables for 5-ply built-up sections but does anyone see any reason why a 6-ply would be a problem? Need it for capacity.
As an alternate I could try 2 4-ply built-up beams. Make the 4-ply beams with nails per the code, them thru bolt the two built-up beams together to get a new huge beam??
Thoughts?