cespi82
Materials
- Dec 23, 2009
- 36
Good morning Gentlemen,
The situation is as follow:
- Glycol Absorber Column in a Gas Dehydration Unit operating at 1100 psi and 40 Celsius degrees
- Service: Wet Gas with around 400 ppm H2S
- Commissioned in 1979, over 35 years in continue operation
- Material of Construction: SA-516-70
- No History of failures or corrosion issues
- Internal visual inspection revealed no presence of bulging / blisters
During the current Turnaround, a UT scanning was conducted for the 1st time at the “Chimney” Tray level. This Chimney Tray is basically where liquids (Glycol + Water) accumulates. So I presume if there is a potential of Wet H2S damage to occur, it is going to be here.
As a result of the UT Scanning several indications, lamination/inclusion like, were found in this area. Phased Array UT scanning was carried out finding a great extent of indications that were classified by the NDT technicians as laminations and clustered inclusions. After finding this, inspection was extended to other areas of the column (away from the chimney tray) and laminations were also found. Presumably we are talking here about dirty steel with poor control back in 1979.
They reported a total of 7 considerably big laminations. The report included the lamination sizes (they grouped nearby laminations since some of them were very close to each other and classified them as single ones), and the locations and estimated area of the clusters of inclusion.
With the outcomes of the report I ran FFS as per API-579 Part 13 Level 1 and everything is satisfied but the last condition which refer to a maximum lamination size if the service is Hydrogen Charging. I continued further to Level 2 and did not pass either.
If we take this literally, we have to repair the absorber column and eliminate these indications, which obviously implies a huge and long job with a lot of things to consider.
My question is: if this column have been in this service for such a long period of time (35 years) and these laminations have been there since then and there’s no presence of bulging/blisters, why should we consider repair it? Only because we ran FFS and did not pass?
All parameters for susceptibility of hydrogen charging are met (I think), but there hasn’t been any evidence of this to be happening.
Your comments are highly appreciated!!
The situation is as follow:
- Glycol Absorber Column in a Gas Dehydration Unit operating at 1100 psi and 40 Celsius degrees
- Service: Wet Gas with around 400 ppm H2S
- Commissioned in 1979, over 35 years in continue operation
- Material of Construction: SA-516-70
- No History of failures or corrosion issues
- Internal visual inspection revealed no presence of bulging / blisters
During the current Turnaround, a UT scanning was conducted for the 1st time at the “Chimney” Tray level. This Chimney Tray is basically where liquids (Glycol + Water) accumulates. So I presume if there is a potential of Wet H2S damage to occur, it is going to be here.
As a result of the UT Scanning several indications, lamination/inclusion like, were found in this area. Phased Array UT scanning was carried out finding a great extent of indications that were classified by the NDT technicians as laminations and clustered inclusions. After finding this, inspection was extended to other areas of the column (away from the chimney tray) and laminations were also found. Presumably we are talking here about dirty steel with poor control back in 1979.
They reported a total of 7 considerably big laminations. The report included the lamination sizes (they grouped nearby laminations since some of them were very close to each other and classified them as single ones), and the locations and estimated area of the clusters of inclusion.
With the outcomes of the report I ran FFS as per API-579 Part 13 Level 1 and everything is satisfied but the last condition which refer to a maximum lamination size if the service is Hydrogen Charging. I continued further to Level 2 and did not pass either.
If we take this literally, we have to repair the absorber column and eliminate these indications, which obviously implies a huge and long job with a lot of things to consider.
My question is: if this column have been in this service for such a long period of time (35 years) and these laminations have been there since then and there’s no presence of bulging/blisters, why should we consider repair it? Only because we ran FFS and did not pass?
All parameters for susceptibility of hydrogen charging are met (I think), but there hasn’t been any evidence of this to be happening.
Your comments are highly appreciated!!