charnott
Civil/Environmental
- Apr 11, 2012
- 46
Have a query/accusation from one of the contractors on my scheme that I'd apprecaite some opinion on.
Site is an offshore reclaimed island with approx. 20m of hydraulic placed fill (rainbowed by dredger). Ground improvement by vibrocompaction brings that fill up to ~65% relative density. That fill is then topped with 900mm of the same material (dredged carbonate sand, minimal fines content encountered to date)placed in layers to 95% compaction.
second contractor is required to excavate trenches from this reclaimed level and place precast structures amongst other things. he excavates ~2m (so through the layered fill and into hydraulic fill), compacts the trench base to 95% and begins his construction.
second contractor says he is unable to compact the trench base to 95% and is asserting that this is because the hydraulic fill has not been compacted appropriately (~65%RD).
I dont agree with that assertion on two principles:
1. applied compactive effort by second contractor will compact the fill directly underlying even if it means it has only compacted a crust.
2. this work was undertaken without issue on the previous island which is essentially identical (terms of scale and material properties).
My belief is that the contractor is likley to be guilty of one or both of the following:
1. Inappropriate/insufficient compactive effort
2. Using unrepresentative lab MDD value to assess results of in-situ density (sand replacement).
Bit long-winded and i know there will be some further queries but I'm keen to hear others opinions/thoughts.
Cheers in advance
Site is an offshore reclaimed island with approx. 20m of hydraulic placed fill (rainbowed by dredger). Ground improvement by vibrocompaction brings that fill up to ~65% relative density. That fill is then topped with 900mm of the same material (dredged carbonate sand, minimal fines content encountered to date)placed in layers to 95% compaction.
second contractor is required to excavate trenches from this reclaimed level and place precast structures amongst other things. he excavates ~2m (so through the layered fill and into hydraulic fill), compacts the trench base to 95% and begins his construction.
second contractor says he is unable to compact the trench base to 95% and is asserting that this is because the hydraulic fill has not been compacted appropriately (~65%RD).
I dont agree with that assertion on two principles:
1. applied compactive effort by second contractor will compact the fill directly underlying even if it means it has only compacted a crust.
2. this work was undertaken without issue on the previous island which is essentially identical (terms of scale and material properties).
My belief is that the contractor is likley to be guilty of one or both of the following:
1. Inappropriate/insufficient compactive effort
2. Using unrepresentative lab MDD value to assess results of in-situ density (sand replacement).
Bit long-winded and i know there will be some further queries but I'm keen to hear others opinions/thoughts.
Cheers in advance