Hello,
When designing a pump with a specific HMT (123 m), and we come across a client update (lowering the pump level ΔL=-1.6m),
Suction tie-in point ( with Residual pressure Pr = 15 m minimum) and discharge point elevation are still intact.
Do we need to update the pump spécification : HMT = 124.6 to make up for the loss in elevation
or it is all the same since as we lose in the discharge, we gain in the suction line
Please find attached a simple image to explain the situation