SAS209
Civil/Environmental
- Jan 19, 2024
- 1
Hello,
We have a project where we will be placing 115 pcf lightweight concrete for a hospital, and came across an interesting issue during our preinstall meeting. For background, I am a licensed CE working for a construction management company that also has a self-perform concrete arm.
The engineer specs out 115pcf as the required equilibrium density per ACI 301 (Section 7). ACI 301 references ASTM C567 for lightweight concrete density testing. The testing agency says how they do density testing for lightweight concrete is to take a set of 3 6"x12" cylinders for every ~50yds, takes them back to the lab, and does an oven dry density test. They add 3pcf and that's the equilibrium density they report back to the engineer to determine whether or not the density of the placed (and now hard) concrete is acceptable. They do not take wet density values in the field. They don't do any test densities before the project starts.
However, if you read ACI 301 (at least how I read it), this seems incorrect. ACI seems to say: do a test batch before the project starts, correlate wet/fresh density back to its lab-determined dry density, add 3pcf to determine equilibrium density. Then, when the project starts and the decks are being placed, only take the field wet/fresh density, use it's pre-determined correlation back to equilibrium density, and if it's within +/- 4pcf of the specified equilibrium density, accept it. There is no discussion of taking lab cylinders every pour, baking the cylinders down to oven dry density, and reporting back to the project +3 days after the pour to tell everyone if the density was correct. And this makes sense to me - why would a project want to wait 3+ days to know if they should have rejected the concrete based on density? It's too late.
Can anyone comment on this that has experience with LW concrete density testing? Which way is correct per industry standard?
More supporting info, if needed:
ACI 301: this is a "specification for structural concrete" document, so this is basically used by engineers etc. to tell a contractor how they want concrete work done on a job. Section 7 is specific additional info/requirements for lightweight concrete. Section 7 incorporates all of Sections 1-5 through reference, and only tells you what's additional/different than the basics outlines in Sections 1-5.
Section 7 says:
7.1.3.1 - For lw, need to also submit ASTM C567 density results (before starting the project) such that equilibrium density can be correlated with a fresh density (which will be needed/taken later on during the project in the field).
7.1.3.3 - Architect/engineer needs to review these submittals prior to the project starting
7.2.2.1 - ACI 301 wants equilibrium density to be calculated (not measured) based on either calculated (based on dry material weights per a formula in ASTM 567) or measured (based on baking a cylinder per ASTM 567) oven dry density.
7.3.1.1 - This goes into field quality control using fresh density (+/-4 pcf) correlated back to the acceptable equilibrium.
FYI: This is the only acceptance criteria ACI gives specific for lightweight concrete. Note that it's a field acceptance criteria (not a lab acceptance, like e.g. a cylinder break strength test would be). So, to me, this means the only density to accept/reject lightweight concrete on is based solely on fresh density (during the pour) and it's pre-determined correlation back to an acceptable equilibrium density value. I.e. there's no need to take cylinders for each field pour, send them back to the lab, cure them, bake them, and get an oven dry density.
Side note: this is where we had our challenges at another project. Testing agency reported on oven dry density instead of fresh density with a correlation; caused lots of confusion and cost to us as the contractor.
We have a project where we will be placing 115 pcf lightweight concrete for a hospital, and came across an interesting issue during our preinstall meeting. For background, I am a licensed CE working for a construction management company that also has a self-perform concrete arm.
The engineer specs out 115pcf as the required equilibrium density per ACI 301 (Section 7). ACI 301 references ASTM C567 for lightweight concrete density testing. The testing agency says how they do density testing for lightweight concrete is to take a set of 3 6"x12" cylinders for every ~50yds, takes them back to the lab, and does an oven dry density test. They add 3pcf and that's the equilibrium density they report back to the engineer to determine whether or not the density of the placed (and now hard) concrete is acceptable. They do not take wet density values in the field. They don't do any test densities before the project starts.
However, if you read ACI 301 (at least how I read it), this seems incorrect. ACI seems to say: do a test batch before the project starts, correlate wet/fresh density back to its lab-determined dry density, add 3pcf to determine equilibrium density. Then, when the project starts and the decks are being placed, only take the field wet/fresh density, use it's pre-determined correlation back to equilibrium density, and if it's within +/- 4pcf of the specified equilibrium density, accept it. There is no discussion of taking lab cylinders every pour, baking the cylinders down to oven dry density, and reporting back to the project +3 days after the pour to tell everyone if the density was correct. And this makes sense to me - why would a project want to wait 3+ days to know if they should have rejected the concrete based on density? It's too late.
Can anyone comment on this that has experience with LW concrete density testing? Which way is correct per industry standard?
More supporting info, if needed:
ACI 301: this is a "specification for structural concrete" document, so this is basically used by engineers etc. to tell a contractor how they want concrete work done on a job. Section 7 is specific additional info/requirements for lightweight concrete. Section 7 incorporates all of Sections 1-5 through reference, and only tells you what's additional/different than the basics outlines in Sections 1-5.
Section 7 says:
7.1.3.1 - For lw, need to also submit ASTM C567 density results (before starting the project) such that equilibrium density can be correlated with a fresh density (which will be needed/taken later on during the project in the field).
7.1.3.3 - Architect/engineer needs to review these submittals prior to the project starting
7.2.2.1 - ACI 301 wants equilibrium density to be calculated (not measured) based on either calculated (based on dry material weights per a formula in ASTM 567) or measured (based on baking a cylinder per ASTM 567) oven dry density.
7.3.1.1 - This goes into field quality control using fresh density (+/-4 pcf) correlated back to the acceptable equilibrium.
FYI: This is the only acceptance criteria ACI gives specific for lightweight concrete. Note that it's a field acceptance criteria (not a lab acceptance, like e.g. a cylinder break strength test would be). So, to me, this means the only density to accept/reject lightweight concrete on is based solely on fresh density (during the pour) and it's pre-determined correlation back to an acceptable equilibrium density value. I.e. there's no need to take cylinders for each field pour, send them back to the lab, cure them, bake them, and get an oven dry density.
Side note: this is where we had our challenges at another project. Testing agency reported on oven dry density instead of fresh density with a correlation; caused lots of confusion and cost to us as the contractor.