Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Linking tasks to a seperate project Summary

Status
Not open for further replies.

eski1

Mechanical
Jun 15, 2004
90
Hi

Quite new to project so this might be an easy answer
We have 5 separate Projects on the go , i want to now create a Weekly summary of these to show our client progress but on the summary I might not want to show him all the tasks on that project only specific ones . I have tried creating a new master project and then inserting the other projects as subprojects but if i then update the separate projects with additional tasks will these then show on the Master Project ( which i would want it to )? and if i delete some of the tasks on the Master project that i don't want the customer to see , will these then delete the tasks on the separate projects as well ( which i wouldn't want).

At present i'm having to update the separate project dates then go into the Master summary and update the dates as well which is undesirable.
Sure this must be quite a common thing to want to do.

Thanks in advance
chris
 
Replies continue below

Recommended for you

Forgot to say i'm using Project 2016 on 365
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor