Hello everyone,
I am running a transverse moving load case along the bent cap. I am using Multi step vehicle live load pattern generation.
For one lane: I defined my start distance as 1.75 ft which represent the EOD.
For two lanes: I defined my start distance as 1.75+12ft (lane)
I am trying to figure the impact of it on the duration of loading. My understanding that the duration of loading is simply (span-start distance) / speed. Is my understanding of it correct?
Thanks!
I am running a transverse moving load case along the bent cap. I am using Multi step vehicle live load pattern generation.
For one lane: I defined my start distance as 1.75 ft which represent the EOD.
For two lanes: I defined my start distance as 1.75+12ft (lane)
I am trying to figure the impact of it on the duration of loading. My understanding that the duration of loading is simply (span-start distance) / speed. Is my understanding of it correct?