4thorns
Structural
- Jan 22, 2009
- 152
Hello All. Hypothetical situation. I have a (4)-2x12 built up wood girder. It's part of a floor system and loaded from one side. All members are (theoretically) identical in size and grade and if properly connected, more than capable of carrying the side load. Joists have adequate connection to outer member (Hangers with appropriate nails) to transfer floor loads into first member of the girder.
Now, if the 4 members are not adequately connected there is going to be a failure. That's a given. Well, it failed.
My first instinct was that the first member is acting in single shear with the second. The second with the third and so on. After further thought this seemed to make sense with nails only penetrating 2 plys at a time. If this is the case, then if the first two member connection fails then the rest of the members seem to be irrelevant.
My questions are;
Is my instinct correct in the case of nails?
How would this situation differ if through bolts penetrating all plys were used instead?
Thank you for your time.
Doug
Now, if the 4 members are not adequately connected there is going to be a failure. That's a given. Well, it failed.
My first instinct was that the first member is acting in single shear with the second. The second with the third and so on. After further thought this seemed to make sense with nails only penetrating 2 plys at a time. If this is the case, then if the first two member connection fails then the rest of the members seem to be irrelevant.
My questions are;
Is my instinct correct in the case of nails?
How would this situation differ if through bolts penetrating all plys were used instead?
Thank you for your time.
Doug