engr567
Structural
- Aug 21, 2009
- 96
What is the ideal location of construction joints on a flat slab? Does ACI have any reference on this? In my case, the contractor wants to locate the construction joints at the mid-spans between the columns,; however, I am not comfortable with that because there might be a maximum positive moments depending on the span lengths. What is the industry practice?