I am designing a detention storage pond (pipe storage), the pre-development flow rates are as followa:
years pre-dev flow rate post-dev flow rate
2 0.0000 0.6733
10 0.001 0.9889
25 0.0245 1.2203
100 0.0959 1.4503
the required orifice for adjusting flow rate in pre development for 10 years storm event condition is 3/16 inch that is low below of the requiremnts,i want to put the orifice under the standpipe to start draining my storm runoff at the begining without accumlating any extra water in the pipes, what design measures you guys are suggesting in this case how can we model our stormwater when the peak flow at the predevelopment condition is two low, in addition infilitration is not allowed.
years pre-dev flow rate post-dev flow rate
2 0.0000 0.6733
10 0.001 0.9889
25 0.0245 1.2203
100 0.0959 1.4503
the required orifice for adjusting flow rate in pre development for 10 years storm event condition is 3/16 inch that is low below of the requiremnts,i want to put the orifice under the standpipe to start draining my storm runoff at the begining without accumlating any extra water in the pipes, what design measures you guys are suggesting in this case how can we model our stormwater when the peak flow at the predevelopment condition is two low, in addition infilitration is not allowed.