Hemifun
Structural
- Apr 7, 2007
- 58
I have a small building with CIP concrete walls and a CIP suspended slab. The building is roughly 27'X22' in plan size. The contract called for 3750 psi concrete and the slab was designed with f'c of 3500 psi. The cylinders broke low so we had cores taken. The cores broke at an average of about 1900 psi(56 days). I checked the calcs. and structurally the slab is ok even with the low breaks. I know most will say I need to have the slab removed and replaced but there are dowels all around the perimeter which tie the slab to the walls and replacement would be difficult. What are some cons besides durability for leaving the slab in place? The entrained air is 7%. Any suggestions??