Hello,
I'm working on a large aboveground LPG bulk storage facility (2 x 50,000 Gal bullets), and would like to check the required separation distances between the storage facility elements and drains, sewers and pits, where gas could accumulate should we have any leaks.
The only reference I can find is a 25ft requirement between 'Point of Transfer' and 'Building Openings or Pits at or below the point of transfer'.
Any comments?
Thanks.