cdstan
Civil/Environmental
- Jan 25, 2008
- 10
I am getting very large NEGATIVE deflections for my pier lpile runs when using a pinned head connection (hpile will be encased in concrete approx. 22ft above ground surface). Can I use a fixed-head connection in this case. If I use a pinned head connection, what could I use as a control option, how much deflection should I allow?