Greetings,
I just want to confirm the duration proposed by the contractor to shutdown a LV switchgear to install two new circuit breakers.
Cable glanding 2 hours for each breaker
Breakers installation 4 hours for each breaker
Cable termination 3 hours for each breaker
Torqueing and tagging 1 hours for each breaker
These are the shutdown activities, the cable pulling, scaffolding, etc. will be pre shutdown.
Thanks